First timber arrives on Mediavaert construction site

Date
8 September 2022

In Amsterdam-Duivendrecht, the first timber components have been mounted for the new head office of DPG Media Nederland, Mediavaert. It is the start of an extensive timber construction consisting of no less than 6,500 m3 of wood. With a floor area of ​​44,000 m2, this new center for journalism will be the largest timber-hybrid office in Europe.

The parking garage, ground floor and elevator shafts are constructed from concrete and form the backbone of the complex. From this point, the construction will continue largely in timber, with timber beams, girders and a hybrid-timber floor. The idea is to use wood wherever possible, and steel and concrete where necessary. This leads to a very efficient and sustainable use of materials, less carbon emissions and a rapid construction pace.

“Mediavaert shows it is possible to create a large office building with a sustainable timber construction, focusing on health, greenery and daylight. In this case, the choice for a timber-hybrid structure not only contributes to a circular and efficient building construction, but also to a healthy and comfortable working environment. This makes Mediavaert a great example of integral sustainability.”
– Do Janne Vermeulen, architect/director Team V Architecture

From 2024, the new media hub on Van der Madeweg will house various Dutch editorial offices and radio stations, including de Volkskrant, Trouw, Parool, Qmusic and NU.nl. In addition to workspaces, the building offers test labs, recording studios, meeting rooms, restaurants, an espresso bar and a sparkling indoor event facility on the waterfront. The interaction between voids and other shared spaces ensures an open character and plenty of daylight throughout the building. Green areas inside, around, and on top of the building create an inspiring working environment that promotes the well-being and health of all users.

Mediavaert is a development of ‘Being’ commissioned by DPG Media. Team V is responsible for the architectural and interior design, in collaboration with Arup, DGMR and DELVA Landscape Architecture/Urbanism. Drees & Sommer provides quality assurance from realisation to completion. BESIX NL is responsible for the construction. Mediavaert is expected to be completed by the end of 2023.

View project

Related news

New project Amstelwood in Amstelveen: from gas station to timber hybrid tower

21 November 2023

Do Janne is number 13 in the Sustainable Top 50 by ABN Amro

8 December 2023

Neuron TU/e wins Architecture Masterprize 2023

8 December 2023

HAUT nominated for Mies van der Rohe Award 2024

3 November 2023

MIRT Exploration Multimodal Junction Eindhoven has started

3 November 2023

Do Janne is nominated for the Sustainable 50 by ABN AMRO

2 November 2023

Interview with Do Janne Vermeulen in Trouw: “Creativity is changing perspectives and making connections”

20 September 2023

BREEAM Outstanding Post Construction Certificate for HAUT

19 September 2023

Take a walk through the future Amsterdam South Station

15 September 2023

CrossOver in Het Parool: ‘Opposites Attract’

31 August 2023

New project Amstelwood in Amstelveen: from gas station to timber hybrid tower

21 November 2023

BREEAM Outstanding Post Construction Certificate for HAUT

19 September 2023

Take a walk through the future Amsterdam South Station

15 September 2023

CrossOver in Het Parool: ‘Opposites Attract’

31 August 2023

HAUT is shortlisted the Amsterdam Best New Building Award

19 May 2023

HAUT is category winner BNA Best Building of the Year 2023!

11 May 2023

Opening of Neuron – Eindhoven University of Technology

3 April 2023

Topping out Mediavaert – DPG Media – with art by Frankey

9 February 2023

Get-together of team members the New University Building of VU Amsterdam

20 January 2023

CrossOver Zuidas is taking shape

15 December 2022